This project in Proposition B includes the reconstruction of pavement and subsurface utilities along a segment of Danieldale Road. The proposed configuration will be a four-lane divided roadway with hike and bike trails north and south of the roadway.
(Continued after image)
Bond Program Year: 2018 Proposition: B Project Name: Danieldale Rd. Project Description: Reconstruct street and subsurface utilities to include bike and pedestrian facilities along Danieldale Rd. between Main St. and US 67 Project Status: Substantial Completion Last Modified Date: 07/12/2024
Estimated Design Start: Spring 2019 Estimated Design Completion: Spring 2020 Estimated Construction Schedule: March 2021 –Summer 2024 Estimated Construction Completion: Summer 2024
Engineering & Design: $651,000 ($324K Bond - 4%; $327K Utilities CIP - 4%)
Construction: $7,200,000 ($2.8M Bond - 36%; $4.4M Utilities CIP - 56%)